How to Switch Development Vendors Mid-Project

Practice3 min

In short

First bring every account and the source code under your control, then order an independent audit, and only then hand the project to a new team with a period of overlap and a rollback plan.

The short answer

You can change vendors mid-project without taking the product down if you follow the order: control of assets → audit → handover → overlap → full transition. The main mistake is ending the contract before you actually hold the access, the source code and the documentation.

Step 1. Secure access and code

Before any difficult conversation, make sure everything critical belongs to you, not to the vendor:

  • Repository (GitHub, GitLab, etc.) — your account should own the organization.
  • Hosting and cloud — the account is registered to your company and paid with your card.
  • Domain and DNS — the registrar and the control panel.
  • Databases and backups — you have a fresh copy.
  • Third-party services: payment providers, email, SMS, analytics, app stores, API keys.
  • Design files and documentation.

Build a simple table: service, owner, who has access, date checked. Keep passwords in a company password manager. After the handover, rotate every key and password the previous vendor could see.

Step 2. Run an independent audit

Before the new team writes any code, it needs to know what it is inheriting. An audit answers:

  • Does the project build and run from scratch using the instructions?
  • Does the code in the repository match what runs on the server?
  • Are there tests, CI/CD and an architecture description?
  • Which vulnerabilities and outdated dependencies exist?
  • Which tasks are really done, and which are only marked as done?

The result is an honest picture: what to keep, what to rewrite and how much work is actually left.

Step 3. Organize the knowledge transfer

Even if the relationship is strained, try to agree on a handover period: a few sessions where the previous team walks through deployment, architecture and known issues. Put it in the contract or an addendum.

A minimal handover package:

ItemWhy it matters
Deployment guideThe new team can run the project
Architecture and integrations mapClear view of how parts connect
Known bugs and technical debtNo need to rediscover them
Environment variables (no secrets in chat)The project works on a new server

Step 4. Avoid downtime

  • Do not change infrastructure and team at the same time. Let the new team work on the current servers first; migration is a separate stage.
  • Freeze big releases during the handover and ship only fixes.
  • Prepare a rollback plan: a fresh backup and a way to restore the previous version.
  • Give the new team small starter tasks so they learn the codebase with little risk.

Common mistakes

  • Terminating the contract before getting access.
  • Expecting the new team to move at full speed from day one.
  • Not checking intellectual property: the contract should transfer the rights to the code.
  • Leaving old access active "just in case".

FAQ

Yes, but only after the key access and a copy of the code are already yours. A fair notice and an agreed handover period usually save more time than a sudden break.

We can help with this

If you'd rather get the result than figure it all out yourself — this is what we do every day.

Discuss a project

Read next

Have an idea or a task? Tell us about it

We'll reply within one business day and propose a solution. The consultation is free.